- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether immediate hub design-build-finance-maintain projects will be signed under the existing structure and transferred to the new structure at a later date, and what the implications are of doing this.
Answer
The intention is that any projects that sign under the existing structure including Forfar Academy and Anderson High would transfer to the new structure at a later date.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether, under the Scottish Futures Trust's revised design-build-finance-maintain structure, revenue contributions from the public sector will be greater for capital projects for which all of the capital comes from the private sector, and what assessment it has made of the additional cost.
Answer
No changes are anticipated to the level of unitary charge payable by procuring bodies for the majority of non-profit distributing or hub funded developments. For those projects where capital contributions are no longer being made by the public sector, unitary charge payments will increase commensurately though it is anticipated this will have a relatively small effect across the programme.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether the board of the Scottish Futures Trust's revised design-build-finance-maintain structure will be under private sector control.
Answer
The board of the hub design-build-finance-maintain project companies has always been privately controlled with strong public sector representation. The revised structure seeks to reinforce that position under the new Eurostat guidance.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether the Scottish Futures Trust's revised structure for design-build-finance-maintain projects halves the public sector share of the project from 40% to 20% and, if so, for what reason.
Answer
I refer the member to the answer to question S4W-26455 on 31 July 2015. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at:
www.scottish.parliament.uk/parliamentarybusiness/28877.aspx.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether it considers that the consequence of the changes to the Eurostat designation of capital projects is that a greater percentage of each capital project has to be seen as private sector for it to be deemed off balance sheet.
Answer
Scottish Ministers have authorised the Scottish Futures Trust to take forward changes to the structure of the hub programme of infrastructure projects which reduce the public sector shareholding in the entities set up to deliver individual projects, having considered the implications of the latest changes to Eurostat guidance on the factors that influence classification outcomes. An update was provided to the Finance Committee on 1 June and again on 19 June 2015.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether the Scottish Futures Trust's revised structure for design-build-finance-maintain projects gives a more direct and greater share of each project to the private sector and, if so, for what reason.
Answer
I refer the member to the answer to question S4W-26455 on 31 July 2015. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at:
www.scottish.parliament.uk/parliamentarybusiness/28877.aspx.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government what the (a) construction costs and (b) repayment terms are for each capital project, broken down by (i) time period, (ii) annual revenue repayments and (iii) total revenue repayment over the project lifetime.
Answer
Information relating to those projects which are operational or in construction and which form part of the Scottish Government’s current revenue funded non-profit distribution/hub investment programme is available on the Scottish Government’s website:
www.gov.scot/Topics/Government/Finance/18232/12308
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government which capital projects that were expected to have a financial close in (a) March, (b) April, (c) May, (d) June and (e) July 2015 now have a revised close date due to the changes to the Eurostat designation of capital projects and what the revised dates are.
Answer
At the start of the year, it was anticipated that the following projects would reach financial close as set out in the following table:
| Month | Project |
| January | Forfar Academy |
| February | Inverclyde Health Centre, Baldragon Academy |
| March | NHS Lothian Bundle, Newbattle High School, Anderson High School, Kelso High School, Elgin High School |
| April | - |
| May | - |
| June | Barrhead High School, Our Lady and St Patricks High School |
Forfar Academy reached financial close in June 2015 following completion of an early construction works package and the Anderson High School is due to reach financial close shortly. Other projects have been delayed by a combination of changes to Eurostat guidance and project specific issues. It is too early to provide revised dates for reaching financial close.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 19 June 2015
-
Current Status:
Answered by Fiona McLeod on 7 July 2015
To ask the Scottish Government, further to the answer to question S4W-25981 by Fiona McLeod on 19 June 2015, which other local authorities have negotiated payments.
Answer
Sixty six claims were intimated, including court actions raised, in respect of former residents of Kerelaw Residential School. Glasgow City Council paid out settlement in 30 of the cases which amounted to £223,826.95 including court expenses.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Thursday, 04 June 2015
-
Current Status:
Answered by Joe FitzPatrick on 2 July 2015
To ask the Scottish Government what consultations it has undertaken since 2011; how many responses it received for each consultation, and when it published those responses.
Answer
All consultations and published responses can be found on the Scottish Government website via the following link: http://www.gov.scot/Publications/.