- Asked by: Thomas Kerr, MSP for Glasgow, Reform UK
-
Date lodged: Wednesday, 18 November 2026
-
Current Status:
Due to be taken in the Chamber on 25 November 2026
To ask the Scottish Government whether any additional payments were made, or offered, to individuals or contractors in connection with the incorporation of BREEAM environmental certification for the Queen Elizabeth University Hospital.
Answer
Taken in the Chamber on 25 November 2026
- Asked by: Thomas Kerr, MSP for Glasgow, Reform UK
-
Date lodged: Wednesday, 18 November 2026
-
Current Status:
Answer expected on 3 December 2026
To ask the Scottish Parliamentary Corporate Body who is responsible for deciding which paintings, images and sculptures are on display in the Parliamentary building, and what guidelines are used to determine when specific items should be on display.
Answer
Answer expected on 3 December 2026
- Asked by: Thomas Kerr, MSP for Glasgow, Reform UK
-
Date lodged: Tuesday, 03 November 2026
-
Current Status:
Answered by Shirley-Anne Somerville on 16 November 2026
To ask the Scottish Government, regarding funding that has been provided to the Scottish Refugee Council over the last year, (a) how much was provided, (b) for what purpose it was provided, and (c) what assessment has been made of the effectiveness of this funding.
Answer
The Scottish Government provides funding to the Scottish Refugee Council to ensure that all people seeking refugee protection in Scotland are welcomed, protected, and can find safety and support to rebuild their lives in Scotland, contributing to our economy and our communities.
The following table contains a list of Scottish Government grant funding provided to Scottish Refugee Council in financial years 2025-26 and 2026-27. 2025-26 figures reflect actual expenditure claimed, while 2026-27 figures reflect the amounts awarded, given this period is currently in progress. It is a condition of all Scottish Government grants that recipients deliver the objectives set out in the grant offer letter. The funding below has been assessed through grant management, written and financial reporting arrangements and has been deemed effective.
Information on Scottish Government contracts can be found at Home - Public Contracts Scotland
Funding Title | Financial Year | Amount | Purpose |
Supporting Lived Experience Involvement in the Implementation of the New Scots Refugee Integration Strategy and Supporting the Delivery of the New Scots ESOL Conference | 2025-26 | £10,384.33 | To support those with lived experience in the implementation of the New Scots Refugee Integration Strategy and to lead planning of the New Scots ESOL Conference, ensuring consideration is given to the involvement of New Scots. |
Supporting Scottish Government Priorities and the New Scots Refugee Integration Strategy Supporting Scottish Government Priorities and the New Scots Refugee Integration Strategy | 2025-26 | £367,520.87 | Support the delivery of the New Scots Refugee Integration and Warm Scots Future strategies to improve New Scots integration in Scotland. Promote the benefits that New Scots bring to communities across Scotland to enhance public perception and support for refugee integration. Engage with practitioners, decision makers and refugee leaders at local, regional and national levels to support, co-ordinate, deliver and inform the actions in the New Scots Refugee Integration Strategy and other associated strategies. |
2026-27 | £400,000 | Support the delivery of the New Scots Refugee Integration and Warm Scots Future strategies to improve New Scots integration in Scotland. Promote the benefits that New Scots bring to communities across Scotland to enhance public perception and support for refugee integration. Engage with practitioners, decision makers and refugee leaders at local, regional and national levels to support, co-ordinate, deliver and inform the actions in the New Scots Refugee Integration Strategy and other associated strategies, as well as inform policy development on emerging priorities. |
Supporting Lived Experience Involvement in Implementing the New Scots Refugee Integration Strategy and Engagement for the Development of the Second New Scots Delivery Plan | 2026-27 | £29,363 | To support those with lived experience in the implementation of the New Scots Refugee Integration Strategy; to support those with lived experience to lead and participate in engagement sessions for development of the second New Scots Delivery Plan; and to support New Scots to be meaningfully involved in Scottish policy development and implementation. |
- Asked by: Thomas Kerr, MSP for Glasgow, Reform UK
-
Date lodged: Wednesday, 11 November 2026
-
Current Status:
Taken in the Chamber on 17 November 2026
To ask the Scottish Government what assessment it has made of the first phase of The Independent Inquiry into White Working Class Educational Outcomes, including whether there are any comparable themes in Scotland.
Answer
Taken in the Chamber on 17 November 2026
- Asked by: Thomas Kerr, MSP for Glasgow, Reform UK
-
Date lodged: Monday, 12 October 2026
-
Current Status:
Answered by Angela Constance on 5 November 2026
To ask the Scottish Government what assessment it has made of any impact of the achievement of BREEAM environmental sustainability standards on the prioritisation of patient safety, infection prevention and clinical requirements during the design and construction of the Queen Elizabeth University Hospital, and whether any steps are being taken to ensure that environmental certification does not compromise patient care and safety in the design and construction of NHS facilities.
Answer
The Scottish Government has made no assessment which concludes that achievement of BREEAM environmental sustainability standards was prioritised over patient safety, infection prevention and control, or clinical requirements during the design and construction of the Queen Elizabeth University Hospital. BREEAM is an environmental assessment methodology intended to support the delivery of sustainable buildings. It is not intended to replace or take precedence over clinical, patient safety, infection prevention and control, statutory or other technical requirements.
NHS healthcare facilities are designed and constructed in accordance with a range of standards, guidance and technical requirements. Patient safety, infection prevention and control, and the delivery of safe and effective clinical services remain fundamental considerations throughout the design, construction and operation of healthcare facilities.
The Scottish Hospitals Inquiry is examining matters relating to the planning, design, construction, commissioning and maintenance of the Queen Elizabeth University Hospital campus and it would not be appropriate to pre-empt the Inquiry's findings.
The Scottish Government remains committed to considering carefully any recommendations arising from the Inquiry and to ensuring that lessons identified are reflected, where appropriate, in the planning, design and delivery of future healthcare infrastructure projects.
- Asked by: Thomas Kerr, MSP for Glasgow, Reform UK
-
Date lodged: Wednesday, 14 October 2026
-
Current Status:
Answered by Neil Gray on 28 October 2026
To ask the Scottish Government, further to the answer to question S7W-04031 by Neil Gray on 14 October 2026, and in light of HMP Barlinnie recently holding 1,450 prisoners and HMP Glasgow having a planned operational capacity of 1,344, (a) whether it will provide details of where the prisoners currently accommodated at HMP Barlinnie will be transferred to upon its closure, (b) what assessment it has made of the capacity available at other Scottish prisons to accommodate any shortfall and (c) whether the stated increase of 357 places refers to the net increase in design capacity across the prison estate or the number of additional prisoners that HMP Glasgow can accommodate compared with HMP Barlinnie.
Answer
I recognise the challenges posed by the current prison population pressures, which is why Scottish Government and the Scottish Prison Service (SPS) have taken a number of actions, including increasing capacity across the current estate by 640 places over the past three years. HMP Glasgow itself will deliver 357 additional spaces to the prison estate based on design capacity, thus increasing the net design capacity.
SPS continually assess capacity throughout their estate to maximise the use of all space. These assessments will form part of SPS’ transition arrangements as and when the time comes to relocate those housed in HMP Barlinnie.
In addition to this, the affordability and deliverability of additional capacity within the prison estate is now being considered, including the possible use of temporary modular accommodation and building of additional house blocks at existing sites.
- Asked by: Thomas Kerr, MSP for Glasgow, Reform UK
-
Date lodged: Thursday, 01 October 2026
-
Current Status:
Answered by Shirley-Anne Somerville on 22 October 2026
To ask the Scottish Government whether it will consider establishing a national framework for recording accessible and adapted social housing.
Answer
Scottish Government recognises the importance of accessible and adapted housing in supporting people to live independently in their communities. This is why we have protected the Registered Social Landlords (RSLs) Adaptations Programme budget, maintaining this at £20.9 million for 2026-27.
While we have no plans to establish a national framework for recording accessible and adapted social housing, we are, however, committed to making accessibility a mainstream feature of all new homes. To this end, we have delivered the first milestone in our 100-day commitment to improve the accessibility, adaptability and usability of Scotland’s homes. Specialists have been appointed to support the review and modernisation of the Housing for Varying Needs design guide, a key reference document for the affordable housing sector in Scotland, and to progress our commitment to deliver a new all-tenure Scottish Accessible Homes Standard through updates to building standards and guidance. A dedicated working group, bringing together industry stakeholders, healthcare professionals, academia and people with lived experience, will help shape the future direction of this work ahead of a public consultation on detailed proposals planned for early 2027.
- Asked by: Thomas Kerr, MSP for Glasgow, Reform UK
-
Date lodged: Wednesday, 21 October 2026
-
Current Status:
Taken in the Chamber on 29 October 2026
To ask the Scottish Government what consideration it gives to responses received through public consultations when making policy decisions.
Answer
Taken in the Chamber on 29 October 2026
- Asked by: Thomas Kerr, MSP for Glasgow, Reform UK
-
Date lodged: Monday, 28 September 2026
-
Current Status:
Answered by Mairi McAllan on 15 October 2026
To ask the Scottish Government, for each of the last 10 years, how many school leavers were recorded as White Scottish males from deprived backgrounds, and of those pupils how many progressed to (a) any positive destination, (b) full-time employment, (c) part-time employment, (d) further education, (e) higher education and (f) a destination that was not classified as positive.
Answer
The following table provides the details requested, where available.
It is not possible to distinguish between full-time and part-time employment so a single row has been included for employment.
Initial Destinations of male school-leavers with White Scottish ethnicity, residing in SIMD Quintile 1, 2015-16 to 2024-25
| | 2015-16 | 2016-17 | 2017-18 | 2018-19 | 2019-20 | 2020-21 | 2021-22 | 2022-23 | 2023-24 | 2024-25 |
| | Percentages |
(a) All Positive Destinations[1] | 86.7 | 87.5 | 88.0 | 90.7 | 87.3 | 91.2 | 91.6 | 92.7 | 92.2 | 92.2 |
(b) & (c) Employment | 25.9 | 25.3 | 24.1 | 26.7 | 18.9 | 28.8 | 31.3 | 30.2 | 28.6 | 25.8 |
(d) Further Education | 34.5 | 35.8 | 37.0 | 36.8 | 38.1 | 32.8 | 34.1 | 34.6 | 33.6 | 37.0 |
(e) Higher Education | 17.1 | 17.5 | 17.5 | 16.4 | 17.2 | 18.3 | 16.6 | 16.6 | 16.7 | 16.6 |
(f) All Other Destinations [2] | 13.3 | 12.5 | 12.0 | 9.3 | 12.7 | 8.8 | 8.4 | 7.3 | 7.8 | 7.8 |
Number of Leavers | 4650 | 4716 | 4388 | 4350 | 4295 | 4374 | 4850 | 4818 | 4746 | 4514 |
[1] Positive destinations include: higher education, further education, training, employment, voluntary work, personal skills development and (between 2010-11 and 2017-18) activity agreements.
[2] Other destinations include: unemployed seeking, unemployed not seeking and unknown.
The proportion in positive destinations has increased by 5.5 percentage points between 2015-16 (86.7%) and 2024-25 (92.2%). This compares to an increase of 2.2 percentage points over the same period for all school-leavers.
- Asked by: Thomas Kerr, MSP for Glasgow, Reform UK
-
Date lodged: Tuesday, 06 October 2026
-
Current Status:
Answered by Neil Gray on 14 October 2026
To ask the Scottish Government where prisoners currently accommodated within the HMP Barlinnie estate will be held following the closure of HMP Barlinnie, in light of a response to a recent Freedom of Information request which revealed that the establishment recently held 1,450 prisoners, while the replacement HMP Glasgow will have 106 fewer places with a planned operational capacity of 1,344 places.
Answer
As an Executive Agency of the Scottish Government the Scottish Prison Service (SPS) has responsibility for the operation of prisons.
As a replacement for HMP Barlinnie, HMP Glasgow, will deliver a modern, safe and secure accommodation that increases the overall design capacity by 357 spaces.
Detailed transition arrangements for the opening of HMP Glasgow are currently being developed by the SPS National Population Management Team, and consideration of prisoner allocation across the prison estate will form part of this planning. This work forms part of a wider SPS initiative to maximise useable capacity throughout the prison estate.