- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Wednesday, 09 September 2026
-
Current Status:
Answered by Stephen Gethins on 22 September 2026
To ask the Scottish Government when the contracts for future Community and Renewable Energy Scheme (CARES) funding delivery are due for renewal.
Answer
The current contract for the administration of the Community and Renewable Energy Scheme (CARES) runs from 1 April 2025 to 31 March 2029. Any new contract would commence on 1 April 2029, following a competitive procurement process.
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Thursday, 17 September 2026
-
Current Status:
Taken in the Chamber on 24 September 2026
To ask the Scottish Parliamentary Corporate Body whether it will consider reviewing the MSP staff travel expenses scheme to ensure that it takes account of the differences in travel distance and costs between geographically smaller parliamentary regions and larger ones, such as the Highlands and Islands.
Answer
Taken in the Chamber on 24 September 2026
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Friday, 17 July 2026
-
Current Status:
Answered by Stephen Gethins on 7 August 2026
To ask the Scottish Government whether it will set out the process by which the Strategic Spatial Energy Plan (SSEP), which it is co-sponsoring with the UK Government, will be approved, and when it expects that process to be concluded.
Answer
The process for the development and approval of the SSEP is set out in the Commissioning letter and the SSEP methodology both of which are publicly available. The decision on the initial pathway for the SSEP will be made by the Secretary of State in autumn 2026, following input from Scottish and Welsh Governments. The finalised Pathway Options Report prepared by NESO will be issued to UK, Scottish and Welsh Government at the end of August. It is expected that the chosen pathway will go out for public consultation in early 2027 with the final SSEP agreed in Autumn 2027.
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Thursday, 30 July 2026
-
Current Status:
Answer expected on 27 August 2026
To ask the Scottish Government what steps it is taking to ensure that local communities are consulted and given an opportunity to bid for leases on publicly owned land where existing wind farms are due to be repowered and the associated land leases are due for renewal.
Answer
Answer expected on 27 August 2026
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Thursday, 30 July 2026
-
Current Status:
Answer expected on 27 August 2026
To ask the Scottish Government what community consultation took place prior to the renewal of the lease for Whitelee Windfarm and whether any opportunities were provided for local community organisations to bid for the lease and, if so, what those opportunities were.
Answer
Answer expected on 27 August 2026
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Thursday, 30 July 2026
-
Current Status:
Answer expected on 27 August 2026
To ask the Scottish Government what steps it is taking to ensure that opportunities for community ownership are maximised as part of the repowering of Whitelee Windfarm.
Answer
Answer expected on 27 August 2026
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Tuesday, 30 June 2026
-
Current Status:
Answered by Stephen Gethins on 28 July 2026
To ask the Scottish Government what progress has been made in taking forward legislative options to allow the escorting of abnormal loads for onshore wind projects by an agency other than Police Scotland or Transport Scotland, and what timeline it is working to for bringing forward any such legislation.
Answer
The Scottish Government recognises the continued pressures facing Police Scotland’s ability to support abnormal load movement requirements for the energy industry and continues to meet regularly with Police Scotland and industry.
The escorting of abnormal loads often requires traffic to be stopped and directed and in Scotland such action can only be undertaken by police officers. The legislation which underpins this requirement is reserved to the UK Government.
The Scottish Government is working closely with the UK Government to identify workable solutions. However, any legislative change in this area would require action by Westminster.
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Tuesday, 30 June 2026
-
Current Status:
Answered by Ivan McKee on 28 July 2026
To ask the Scottish Government what action it is taking to uphold the commitments of the 2023 Scottish Onshore Wind Sector Deal, including the 12-month and 24-month determination targets, and how many applications have (a) met and (b) missed these targets since the sector deal was agreed.
Answer
In recent years, the Energy Consents Unit (ECU) has undergone significant recruitment and training to bolster the workforce and match the rising demand in applications. In addition, the Planning and Infrastructure Act 2025 provided Scottish Ministers with new regulation-making powers that seek to streamline the consenting process. We will consult later this year on how we intend to use these powers, with findings informing secondary legislation. Taken together, these actions will help Ministers meet our ambitions for faster decision-making timescales of onshore wind applications.
The Onshore Wind Sector Deal included the ambition that from 2025 we would aim to determine section 36 applications for new sites and for the re-powering of existing operational sites within 12 months, or 24 months if there is a Public Local Inquiry (PLI). We remain committed to this ambition, ensuring that the energy consenting process delivers timely results and takes a pragmatic approach.
Between January 2025 and June 2026, the ECU received 46 onshore wind applications. By 14 July 2026, at the time of answering:
- none of these applications have been determined
- 27 applications can no longer meet the 12 month determination timescale
- 19 applications remain within 12 month determination timescale
- all applications still remain within the 24 month determination timescale (where a PLI may be required)
This summer, the ECU will publish an Annual Report for the first time which will include data and performance monitoring associated with their work. The report will provide further analysis relating to the factors which impact determination timescales.
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Tuesday, 30 June 2026
-
Current Status:
Answered by Stephen Gethins on 20 July 2026
To ask the Scottish Government what progress it has made towards its target of 20GW of operational onshore wind capacity by 2030, and what assessment it has made of whether current consenting rates are sufficient to meet that target.
Answer
As of the end of Q1 2026, there was 10.7GW of onshore wind installed capacity with an additional 5.9GW awaiting construction and 2.1GW under construction. This gives a total of 18.7GW consented onshore wind capacity across these categories. These figures are taken from publications released by the Department of Energy Security and Net Zero (DESNZ).
It is vital to note that achieving consent is only one of several factors that determine deliverability. Grid availability and a route to market through Contracts for Difference are key factors outwith the Scottish Government’s control.
- Asked by: Kristopher Leask, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Tuesday, 30 June 2026
-
Current Status:
Answered by Stephen Gethins on 20 July 2026
To ask the Scottish Government what role it anticipates the repowering and extension of existing onshore wind sites will play in meeting its target of 20GW of operational onshore wind by 2030, and whether it plans to bring forward enhanced policy support for repowering.
Answer
The Scottish Government recognises the important role that repowering will play in delivering on our onshore wind ambitions.
Scotland’s long-standing support for onshore wind, sustained even when deployment elsewhere in Great Britain stalled, means that most initial repowering opportunities will be in Scotland.
We will continue to consider what additional measures might further support onshore wind deployment in Scotland, including repowering, as we work with industry to deliver our shared ambitions.