- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Submitting member has a registered interest.
-
Date lodged: Thursday, 13 October 2022
-
Current Status:
Answered by Shona Robison on 3 November 2022
To ask the Scottish Government, further to the answer to question S6W-10188 by Shona Robison on 6 September 2022, whether those seven assessments have been finalised, and what the start dates are for the remediation of each of those buildings.
Answer
Remediation is a complex construction task requiring agreement from a number of participants. This includes homeowners, their representatives, architects, construction supply chains, legal representation and those involved in any agreed reconstruction. We are working with stakeholders to ensure, once we have a finalised SBA, we can agree remediation plans.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Submitting member has a registered interest.
-
Date lodged: Thursday, 13 October 2022
-
Current Status:
Answered by Shona Robison on 3 November 2022
To ask the Scottish Government, further to the answer to question S6W-10193 by Shona Robison on 6 September 2022, regarding the single building assessment, what its position is on whether ventilated car parks under buildings may accelerate fire spread.
Answer
It is an engineering decision on areas of risk when completing a Single Building Assessment. The Assessment is a whole building approach, and fire engineers highlight areas of risk to ensure safety for homeowners.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Submitting member has a registered interest.
-
Date lodged: Thursday, 13 October 2022
-
Current Status:
Answered by Shona Robison on 3 November 2022
To ask the Scottish Government what the status is of each (a) single building assessment and (b) single building assessment application it has received under the grant-based approach.
Answer
16 buildings are now in delivery stage with a further 11 buildings finalising applications. We have expanded the pilot to 27 buildings in order to capture an additional building attached to an original pilot building.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Submitting member has a registered interest.
-
Date lodged: Thursday, 13 October 2022
-
Current Status:
Answered by Shona Robison on 3 November 2022
To ask the Scottish Government, further to the answer to question S6W-10193 by Shona Robison on 6 September 2022, regarding the single building assessment, how many queries it has received to date on the potential additional risk of fire spread related to car parks.
Answer
In the programme to date this has been raised twice with regard to buildings participating in the pilot. As part of the building assessment programme we have had discussions with fire engineers when they have raised concerns regarding carparks in buildings.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Submitting member has a registered interest.
-
Date lodged: Thursday, 13 October 2022
-
Current Status:
Answered by Shona Robison on 3 November 2022
To ask the Scottish Government further to the answer to question S6W-10191 by Shona Robison on 6 September 2022, how many of those buildings, which have applied under the grant-based scheme, have received (a) partial and (b) full funding.
Answer
We have made 18 payments so far to 15 buildings, with 10 currently under assessment with a partial payment and 5 with full payment and assessment having concluded. All buildings with cladding concerns have and will continue to be offered fully funded assessments.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Monday, 31 October 2022
-
Current Status:
Taken in the Chamber on 1 November 2022
To ask the Scottish Government what steps it is taking to address the reported findings of an independent review of the cladding remediation programme that “successful delivery of the project is in doubt with major risks or issues apparent".
Answer
Taken in the Chamber on 1 November 2022
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Submitting member has a registered interest.
-
Date lodged: Wednesday, 21 September 2022
-
Current Status:
Answered by Shona Robison on 3 October 2022
To ask the Scottish Government, further to the answer to question S6W-10242 by Shona Robison on 7 September 2022, whether it will publish the (a) average apartment rental charges updated in line with CPI and (b) grant calculations shared with social landlords, for each year since 2017.
Answer
As I noted in my answer to S6W-10242, we are considering publication of average apartment rental charges and grant calculations as part of the current review of the Home Owners Support Fund, which is expected to conclude by Spring 2023. If the decision is taken to publish the figures, this will include historical calculations.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Wednesday, 31 August 2022
-
Current Status:
Answered by Shona Robison on 23 September 2022
To ask the Scottish Government, further to the answer to question S6W-10165 by Shona Robison on 19 August 2022, how many buildings over 11 metres it estimates are affected by combustible cladding.
Answer
As part of the cladding remediation programme we will take a building-by-building approach to assess and gather this information to create a central register. This will include buildings over 11 metres. We expect the majority of buildings to be low risk and require limited or no intervention.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Wednesday, 31 August 2022
-
Current Status:
Answered by Shona Robison on 23 September 2022
To ask the Scottish Government, further to the answer to question S6W-10165 by Shona Robison on 19 August 2022, what (a) assessment, (b) feasibility studies and (c) survey activity it has conducted to determine the number of buildings of 11 metres and over that will require (i) assessment for and (ii) remediation of combustible cladding.
Answer
The work of the cladding remediation programme will gather data as it progresses with Single Building Assessments. This information will be used to build a reliable register of information as set out in the Ministerial Working Group on Mortgage Lending and cladding report in March 2021.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Submitting member has a registered interest.
-
Date lodged: Thursday, 01 September 2022
-
Current Status:
Answered by Shona Robison on 22 September 2022
To ask the Scottish Government, regarding the Home Owners' Support Fund Mortgage to Rent scheme, what the (a) total and (b) average purchase expenditure was, and how many purchases have been made under the scheme, in each year of operation.
Answer
Under the Mortgage to Rent scheme, the Scottish Government subsidise up to 60% of the property value. The total grant includes the purchase subsidy and the cost of repairs required to bring the property up to the Scottish Housing Quality Standard. Further details on how subsidies are calculated can be found in the linked guidance HOSFGN/005 . The following table shows the total and average subsidy paid by the Scottish Government to Registered Social Landlords (RSLs) for each year of operation of Mortgage to Rent.
Mortgage to Rent |
Financial Year | Total Subsidy Expenditure (£m) | Average Subsidy Expenditure (£m) | No. of Homes Purchased |
2008-09 | 15.226 | 0.065 | 233 |
2009-10 | 19.600 | 0.060 | 303 |
2010-11 | 20.097 | 0.052 | 374 |
2011-12 | 14.500 | 0.041 | 325 |
2012-13 | 9.871 | 0.035 | 288 |
2013-14 | 8.274 | 0.031 | 228 |
2014-15 | 5.661 | 0.029 | 192 |
2015-16 | 3.079 | 0.038 | 80 |
2016-17 | 2.980 | 0.046 | 65 |
2017-18 | 1.127 | 0.029 | 39 |
2018-19 | 1.536 | 0.040 | 32 |
2019-20 | 1.191 | 0.058 | 28 |
2020-21 | 0.303 | 0.044 | 8 |
2021-22 | Figures will be published shortly |
Figures for 2021-22 will be published shortly.