- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 16 September 2026
-
Current Status:
Answered by Stephen Flynn on 29 September 2026
To ask the Scottish Government what progress has been made in improving and increasing toilet facilities and access to toilets for train drivers in Scotland.
Answer
These matters fall within the responsibility of train operators in their capacity as employers.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 16 September 2026
-
Current Status:
Answered by Stephen Flynn on 29 September 2026
To ask the Scottish Government what discussions it has had with freight train operating companies about changing schedules for drivers in Scotland to enable better them access to toilets.
Answer
These matters fall within the responsibility of rail freight operators in their capacity as employers.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Monday, 14 September 2026
-
Current Status:
Answered by Stephen Flynn on 28 September 2026
To ask the Scottish Government, regarding the £2 bus fare cap in the Strathclyde Partnership for Transport area, how it has calculated the estimated number of passenger journeys, including any assumptions about passenger demand and the number of eligible journeys.
Answer
As detailed information on commercial bus journeys is not available, estimates were produced using a model developed for the fare cap pilot. The model uses concessionary travel data and local population information to estimate the number of non-concessionary bus journeys across the area. It then compares these estimates with overall bus revenue and applies standard assumptions about how passenger numbers may change in response to lower fares. These estimates were used to calculate the likely number of eligible journeys and the expected cost of the scheme.
Further details will be published in the Outline Business Case for the scheme.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 10 September 2026
-
Current Status:
Answered by Ivan McKee on 25 September 2026
To ask the Scottish Government, further to the evidence given by the Acting Cabinet Secretary for Net Zero and Energy to the Net Zero, Energy and Transport Committee on 14 January 2025 regarding the 52-week target timescale for determining section 36 applications for offshore wind projects under the Electricity Act 1989, how many live applications currently exceed that timescale, broken down by the number for which all statutory consultee responses have been received and how long each such application has been awaiting determination since the final response was received.
Answer
Marine Directorate targets determination of offshore wind applications within 12 months, excluding periods where Additional Information is being prepared and consulted on in accordance with Environmental Impact Assessment regulations, and recognising that some applications are particularly complex.
MD-LOT is currently processing 14 applications. Receipt of all statutory consultee responses does not mean an application is ready for a determination. Of the 3 applications which exceed the 12 month target, engagement with statutory consultees is ongoing on Marine Protected Area Assessments, Appropriate Assessments and Derogation Cases until shortly before a recommendation is provided to Ministers.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 16 September 2026
-
Current Status:
Answered by Ivan McKee on 24 September 2026
To ask the Scottish Government what guidance and advice it provides to civil servants on maintaining their impartiality when creating and promoting digital content and advertising that promotes its agenda.
Answer
Civil servants must adhere to the civil service code of conduct and carry out their duties with integrity, honesty, objectivity and impartiality. Scottish Government Internal and leadership communications routinely highlight the code to staff. In addition, all Scottish Government communicators (including those creating digital content and advertising) follow the guidance from the UK Government’s Government Communication Service which provides Propriety and ethics in government communications - Government Communications in addition to the code. The Government has a responsibility to inform the public of policy and the Government may use a variety of media, including paid and unpaid publicity, to achieve its objectives.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 10 September 2026
-
Current Status:
Answered by Ivan McKee on 24 September 2026
To ask the Scottish Government, further to the evidence given by the Acting Cabinet Secretary for Net Zero and Energy to the Net Zero, Energy and Transport Committee on 14 January 2025 regarding the 52-week target timescale for determining section 36 applications for offshore wind projects under the Electricity Act 1989, how many applications have been determined in that timescale, and what the average determination time was for applications that exceeded it.
Answer
The 52-week ambition discussed in Committee evidence relates to onshore wind farm applications under the Onshore Wind Sector Deal. The position for offshore wind projects is different and is set out below.
The average determination timeline for the 15 offshore windfarm applications determined by Scottish Ministers since 2015 is 11 months excluding any time taken to receive and consult upon Additional Information, as required under the EIA regulations. The average determination time for applications that exceeded 12 months was 17 months, excluding any time taken to receive and consult upon Additional Information.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Thursday, 10 September 2026
-
Current Status:
Answered by Ivan McKee on 24 September 2026
To ask the Scottish Government, further to the evidence given by the Acting Cabinet Secretary for Net Zero and Energy to the Net Zero, Energy and Transport Committee on 14 January 2025 regarding the 52-week target timescale for determining section 36 applications for offshore wind projects under the Electricity Act 1989, how many live applications remain on track to be determined within that timescale.
Answer
The 52-week ambition discussed in Committee evidence relates to onshore wind farm applications under the Onshore Wind Sector Deal. The position for offshore wind projects is different and is set out below.
Best efforts are made to meet determination timeline of 12 months from initial application, excluding time taken to receive and consult upon Additional Information, as required under the EIA regulations. We are clear that more complex applications may take longer. Of the current live offshore windfarm applications, 10 of 13 are currently projected to be determined within 12 months, excluding time to receive and consult upon Additional Information and resolution of other complexities.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 16 September 2026
-
Current Status:
Answered by Ivan McKee on 24 September 2026
To ask the Scottish Government how much it spent on digital advertising to promote the Programme for Government, broken down by platform.
Answer
The total spend to increase public awareness of the government’s programme was £102,467.90 of which £22,392 was spent on production and £80,075.90 on paid media.
Media costs are broken down by platform as requested;
Meta £43,602.38
Numodo (YouTube) £34,000.00
TikTok £2,473.52
Total £80,075.90
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 16 September 2026
-
Current Status:
Answered by Ivan McKee on 24 September 2026
To ask the Scottish Government how many digital adverts it has created to promote its Programme for Government and related policy announcements.
Answer
Four adverts were created to increase public awareness of the government’s programme;
- Programme for Government – overall summary
- Programme for Government – Parental focus
- Programme for Government – Health focus
- Programme for Government - Net Zero focus
Each had a video and a static, so eight adverts in total.
- Asked by: Daniel Johnson, MSP for Edinburgh Southern, Scottish Labour
-
Date lodged: Wednesday, 09 September 2026
-
Current Status:
Answered by Stephen Gethins on 24 September 2026
To ask the Scottish Government how many Warmer Homes Scotland grants have been approved by Home Energy Scotland, and what percentage have been subsequently withdrawn or not taken up, in each year since 2023.
Answer
Warmer Homes Scotland is delivered through a managed service contract with our delivery partner, Warmworks, rather than through grant payments to households.
The data below relates to the current version of the scheme, which began in October 2023. Households interested in the scheme first contact Home Energy Scotland (HES), which carries out an initial eligibility assessment and refers potentially eligible households to Warmworks. Warmworks then undertakes a more detailed assessment of the property and household circumstances before confirming eligibility and progressing any installations.
The figures below show:
- the number of referrals received from Home Energy Scotland;
- the number of referrals that did not ultimately proceed to installation (including cases where households were found not to be eligible, technical issues prevented delivery, or the household chose not to continue); and
- the number of households where energy efficiency or heating installations were completed.
Please note that referrals do not always complete within the same financial year in which they are received. As a result, the figures in each column should not be compared directly.
Period | Referrals received from Home Energy Scotland | Referrals not progressing to installation* | Households with completed installations |
April 2026 to July 2026 | 3,070 | 1,161 | 2,022 |
April 2025 to March 2026 | 9,289 | 3,949 | 6,270 |
April 2024 to March 2025 | 9,008 | 7,694** | 7,334 |
October 2023 to March 2024 | 11,058 | 1,388 | 1,173 |
* Includes households that were found not to be eligible, applications that could not proceed for technical reasons, and households that chose not to continue with the scheme.
** The current scheme launched in October 2023 with a large backlog of applications carried forward from the previous scheme period. As a result, a significant number of older applications were assessed and closed during 2024-25, increasing the number reported as not progressing to installation in that year.